100128-01_0In answer to a recent question on the website, Executive Director of Special Projects Ron Urice (who is overseeing the project for Immanuel) wrote recently:

The B-Wing (which we are working on now) should be ready to occupy early April 2010, if all goes well. Weather, late supplies and such can delay any building project, but at present, we look to be on schedule.

Once we occupy the B-Wing, work will begin on the A-Wing, Gym and Atrium (Multi-purpose Room). The Gym and A-Wing should take about 11 months, then we will start on the Narthex and Fireside Room areas while we finish up the Atrium. If all of this goes on schedule, we should finish the presently contracted project around December 2011.

Once this project is completed, refurbishment and upgrades to the Worship Center will be considered. That decision will be made by the Elders and the congregation as need and availability of funds would dictate.